Sixty Five Broadway is a luxurious pre-construction condominium development at the heart of midtown Toronto. With distinctive towers soaring above a four-storey podium, a private courtyard off Broadway is your tranquil oasis from the action of Yonge and Eglinton. The landscaping is soothing and minimal with manicured walkways and seasonal plantings. Beauty and serenity are by your side as you arrive home.

location
65 Broadway Avenue, Toronto
Status
Under Construction
Tentative Completion Date
2025 – 2026*
Architect
Wallman Architects
Interiors
Tomas Pearce
Landscape
Studio TLA
Units
389
Type
High-Rise Residential
Construction Update
As of March 18, 2025
Sixty Five Broadway is reaching new heights—inside and out. The exterior is now fully complete, revealing the sleek, modern façade that adds beauty to the Yonge and Eglinton skyline. With concrete forming, window installation, and the building envelope all finalized, the final finishes indoors continues. Mechanical and electrical finishing are progressing steadily, while drywall is nearing completion on the upper floors. Every step brings us closer to unveiling this stunning new residence. Stay connected for the latest updates as we move toward the final stages of construction! Follow us on Instagram and YouTube to stay up-to-date and learn more about these and other upcoming projects.
- Zoning Bylaw (Complete)
Formal Zoning By-law was issued on March 12, 2021.
- Construction Management Plan (Complete)
Our Construction Management Plan has been approved by City staff and Community Council approval on June 2021
- Notice of Approval Conditions Status (Complete)
Received its Notice of Approval Conditions (NOAC) on April 21, 2021.
- Building Permit
Received Demolition Permit on May 28, 2021 and Shoring & Excavation Permit on May 25, 2021. Received Foundation Permit on October 26, 2022.
- Site Plan Approval (Complete)
Received Site Plan Agreement on December 9, 2022.
Construction Status
- Concrete Forming: Complete on all floors
- Window Installation: Complete on all floors
- Building Envelope: Complete on all floors
- Mechanical Rough-in: Complete up to 21st floor
- Electrical Rough-in: Complete up to 20th floor
- Drywall: Complete up to 38th floor
*The completion dates above are estimates only, subject to change from time to time by the vendor without notice, and the vendor makes no representations or warranties with respect to the completion of the project except as set out in a fully executed Agreement of Purchase and Sale. No such estimate shall amend or modify the Statement of Critical Dates provided in any Agreement of Purchase and Sale which shall be deemed conclusive of any obligation relating to the completion timeline of the project. Please consult a sales representative for more details.
Careers
Want to Work With Us?
Life Construction is always on the look out for passionate individuals who enjoy working in challenging environments.