A landmark new address in Uptown Markham, Riverview is a stunning statement of success in one of Canada’s most desired communities. Here you will discover the consummate balance of historic village charm and modern energy. Live a short stroll from superb restaurants, unique shops, world-class products at Whole Foods and fine wines at the neighbouring LCBO. Explore green swaths of river lands from Unionville’s famed Toogood Pond to the Rouge River Valley right here in your own backyard. Smart. Sophisticated. Refined. Distinctive. Riverview.

Virtual Tours

location

Hwy 7 & Verdale Crossing, Markham

Status

Under Construction

Tentative Completion Date

2024*

Architect

Kirkor Architects + Planners

Interiors

Tomas Pearce Interior Design

Landscape

Schollen & Company Inc.

Units

1,042

Type

High-Rise Residential

Construction Update

Q1/Q2 2022

At Riverview, construction of Building C is almost complete and occupancy on the lower floors began in early June 2022. T2 Condo Rentals has pre-leased over 50 units with the majority of the approved tenants moving in within days’ of unit occupancy commencement. At Building A, concrete forming and windows are complete with mechanical and electrical rough-ins continuing. At Building B, concrete forming is also complete with window installation and building envelope construction continuing. Occupancies for all buildings are ongoing until Q4 2023.

Building C

  • Concrete forming, windows, building envelope, mechanical and electrical rough-ins, drywall, tile, flooring, cabinets, trim carpentry and green roof all complete
  • PDI’s started on May 3rd and currently on 10th floor
  • Occupancies started On June 7th and currently on 6th floor

Building A

  • Concrete forming completed on all floors
  • Window installation completed on all floors
  • Building envelope completed up to 40th floor
  • Mechanical rough-in completed up to 20th floor
  • Electrical rough-in completed up to 19th floor
  • Drywall up complete up to 16th floor
  • Tile installation completed up to 11th floor
  • Trim carpentry completed up to 11th floor

Building B

  • Concrete forming completed on all floors
  • Window installation completed up to 38th floor
  • Building envelope completed up to 11th floor
  • Mechanical rough-in completed up to 7th floor
  • Electrical rough-in completed up to 6th floor
  • Drywall started on 2nd floor

Landscaping

  • Progress for hard landscaping stands at 70%

*The completion dates above are estimates only, subject to change from time to time by the vendor without notice, and the vendor makes no representations or warranties with respect to the completion of the project except as set out in a fully executed Agreement of Purchase and Sale. No such estimate shall amend or modify the Statement of Critical Dates provided in any Agreement of Purchase and Sale which shall be deemed conclusive of any obligation relating to the completion timeline of the project. Please consult a sales representative for more details.