Sixty Five Broadway

Residential

Sixty Five Broadway

Sixty Five Broadway is a luxurious pre-construction condominium development at the heart of midtown Toronto. With distinctive towers soaring above a four-storey podium, a private courtyard off Broadway is your tranquil oasis from the action of Yonge and Eglinton. The landscaping is soothing and minimal with manicured walkways and seasonal plantings. Beauty and serenity are by your side as you arrive home.

location

65 Broadway Avenue, Toronto

Status

Under Construction

Tentative Completion Date

2024 – 2025*

Architect

Wallman Architects

Interiors

Tomas Pearce

Landscape

Studio TLA

Units

389

Type

High-Rise Residential

Construction Update

Q3/Q4 2021

At Sixty Five Broadway, Demolition commenced on July 2, 2021 and completed on October 29, 2021. The Construction Team is preparing the site to commence Shoring and Excavation which will be ready by the week of 15th of November 2021.

  • Zoning Bylaw (Complete)
    Formal Zoning By-law was issued on March 12, 2021.
  • Construction Management Plan (Complete)
    Our Construction Management Plan has been approved by City staff and Community Council approval on June 2021
  • Notice of Approval Conditions Status (Complete)
    Times received its Notice of Approval Conditions (NOAC) on April 21, 2021.
  • Building Permit
    Times received Demolition Permit on May 28, 2021 and Shoring & Excavation Permit on May 25, 2021
  • Site Plan Review (Complete) / Site Plan Approval (Pending)
    Site Plan Approval and a formal agreement remain pending and are expected to be finalized in Spring 2022. This approval and formal agreement will not delay the demolition mobilization or construction commencement.

*The completion dates above are estimates only, subject to change from time to time by the vendor without notice, and the vendor makes no representations or warranties with respect to the completion of the project except as set out in a fully executed Agreement of Purchase and Sale. No such estimate shall amend or modify the Statement of Critical Dates provided in any Agreement of Purchase and Sale which shall be deemed conclusive of any obligation relating to the completion timeline of the project. Please consult a sales representative for more details.

Careers

Want to Work With Us?

Life Construction is always on the look out for passionate individuals who enjoy working in challenging environments.

Pavilia Towers

Residential

Pavilia Towers

Standing proudly above the rest, the two remarkable buildings of Pavilia Towers reach up into the sky a full 41 and 38 storeys. That means our extraordinary views stretch out to the horizon, sunsets linger longer and the first rays of the morning sun touch Pavilia Towers while the rest of the city is still asleep. Tall, graceful, stately and elegant, this is the very pinnacle of living.

location

Hwy 7 & South Park Road, Thornhill

Status

Under Construction

Tentative Completion Date

2022*

Architect

Icke Brochu Architects Inc.

Interiors

N/A

Landscape

Schollen & Company Inc.

Units

769

Type

High-Rise Residential

Construction Update

Q3/Q4 2021

At Pavilia Towers, construction at Building A has reached a significant milestone with all forming completed, tower crane removed and window installations complete. Suite electrical and mechanical rough-ins has reached level 15, drywall has reached level 11 and exterior walls complete up to level 28. Forming at Building B is complete with precast reaching level 8 with a focus now turning to in-suite electrical and mechanical, drywall and window installation.

Building A

  • Forming completed and tower crane removed
  • Precast completed other than hoist units
  • Mechanical and electrical in slab rough ins completed
  • Suites mechanical and electrical rough ins at 15th floor
  • Interior drywall at 11th floor
  • Exterior drywall at 28th floor
  • Window installation complete other than hoist units

Building B

  • Forming completed
  • Precast up to 8th floor
  • Mechanical and electrical in slab rough ins completed
  • Suites mechanical and electrical rough ins not started
  • Interior drywall not started yet
  • Exterior drywall not started yet
  • Window Installation 3rd floor

*The completion dates above are estimates only, subject to change from time to time by the vendor without notice, and the vendor makes no representations or warranties with respect to the completion of the project except as set out in a fully executed Agreement of Purchase and sale. No such estimate shall amend or modify the Statement of Critical Dates provided in any Agreement of Purchase and Sale which shall be deemed conclusive of any obligation relating to the completion timeline of the project. Please consult a sales representative for more details.

Careers

Want to Work With Us?

Life Construction is always on the look out for passionate individuals who enjoy working in challenging environments.

Riverview

Residential

Riverview

A landmark new address in Uptown Markham, Riverview is a stunning statement of success in one of Canada’s most desired communities. Here you will discover the consummate balance of historic village charm and modern energy. Live a short stroll from superb restaurants, unique shops, world-class products at Whole Foods and fine wines at the neighbouring LCBO. Explore green swaths of river lands from Unionville’s famed Toogood Pond to the Rouge River Valley right here in your own backyard. Smart. Sophisticated. Refined. Distinctive. Riverview.

location

Hwy 7 & Verclaire Gate South, Markham

Status

Under Construction

Tentative Completion Date

2021 – 2022*

Architect

Kirkor Architects + Planners

Interiors

Tomas Pearce Interior Design

Landscape

Schollen & Company Inc.

Units

1,042

Type

High-Rise Residential

Construction Update

Q3/Q4 2021

At Riverview, Building C has reached rooftop with window installation fully complete. Interior finishing continues with suite mechanical and electrical rough in reaching penthouse level, drywall complete to level 17, flooring complete to level 12, cabinets installed to level 7 and the green roof 80% complete. Building A concrete forming is continuing at roof level with building envelope complete to the 12th level. Building B concrete forming has reached level 26 with building envelope complete to level 6.

Building C

  • Windows installation is completed
  • Suites mechanical and electrical rough in up to Penthouse level
  • Drywall has been completed up to level 17
  • Flooring is continuing at level 12
  • Cabinets have been installed up to level 7
  • Trim carpentry is being worked up to level 15
  • Green roof stands at 80%

Building A

  • Concrete forming is continuing at roof level
  • Mechanical and electrical rough in up to level 5
  • Building envelope up to level 12

Building B

  • Concrete forming up to level 26
  • Building envelope up to level 6

Landscaping

  • Progress for hard landscaping stands at 40%

*The completion dates above are estimates only, subject to change from time to time by the vendor without notice, and the vendor makes no representations or warranties with respect to the completion of the project except as set out in a fully executed Agreement of Purchase and Sale. No such estimate shall amend or modify the Statement of Critical Dates provided in any Agreement of Purchase and Sale which shall be deemed conclusive of any obligation relating to the completion timeline of the project. Please consult a sales representative for more details.